Type: IP (Integer Programming)
This handbook explains the Workforce Scheduling sample problem in the LP Black Box platform.
Schedule staff using three types of workers to meet coverage needs at minimum cost.
| Worker Type | Cost per Day ($) | Coverage Units |
|---|---|---|
| Full-Time (FT) | 200 | 8 |
| Part-Time (PT) | 100 | 4 |
| Temporary (Temp) | 50 | 2 |
Minimize total labor cost while meeting coverage requirements.
Coverage: Need at least 80 coverage units
Formula: 8×FT + 4×PT + 2×temp ≥ 80
Max Full-Time: Cannot hire more than 15 FT workers
Formula: FT ≤ 15
Max Part-Time: Cannot hire more than 20 PT workers
Formula: PT ≤ 20
Select Workforce Scheduling from the dropdown.
The solver finds the optimal mix of workers to meet coverage at lowest cost.
This demonstrates labor scheduling with different worker types and constraints.